Multi-Objective Optimization of Inverter Siting and Collector-Cable Routing for Fixed-Topology Offshore Floating Photovoltaic Plants with Inter-Block Gap Allowance

Article Open Access

Multi-Objective Optimization of Inverter Siting and Collector-Cable Routing for Fixed-Topology Offshore Floating Photovoltaic Plants with Inter-Block Gap Allowance

Author Information
1
Tianjin Key Laboratory of New Energy Power Conversion, Transmission and Intelligent Control, Tianjin University of Technology, Tianjin 300384, China
2
School of Ocean Energy, Tianjin University of Technology, Tianjin 300384, China
3
National Industry-Education Platform of Energy Storage, Tianjin University, Tianjin 300072, China
4
National Science Center for Earthquake Engineering, Tianjin University, Tianjin 300350, China
*
Authors to whom correspondence should be addressed.

Received: 28 August 2026 Revised: 07 September 2026 Accepted: 08 October 2026 Published: 15 October 2026

Creative Commons

© 2026 The authors. This is an open access article under the Creative Commons Attribution 4.0 International License (https://creativecommons.org/licenses/by/4.0/).

Views:18
Downloads:10
Mar. Energy Res. 2026, 3(4), 10021; DOI: 10.70322/mer.2026.10021
ABSTRACT: Offshore floating photovoltaic (OFPV) plants require cable allowance at interfaces between floating blocks to support maintenance access and accommodate relative motion. Because synchronized relative-motion records are often unavailable during early design, this allowance cannot be calibrated directly. This study proposes a fixed-topology multi-objective method for joint inverter siting and low-voltage collector-cable routing. CAD polylines are decomposed into fixed segments, and route-specific inter-block crossings, and a bounded gap-allowance factor is applied only at the crossings. NSGA-II generates nondominated layouts that minimize cable investment and the present value of resistive-loss cost while satisfying equipment-capacity, string-count, current, and voltage-drop constraints. The method is applied to a 5.1212 MWp grid-connected OFPV plant under the nominal routing case (γs = 1). Compared with the manual design, the selected compromise layout reduces collector-cable investment by 7.0% and the present value of power-loss cost by 14.9%, producing a 9.76% reduction in the modeled total collection-system cost. The results demonstrate the economic value of coordinated inverter siting and cable routing while identifying the data required for future dynamic-allowance calibration.
Keywords: Offshore floating photovoltaic; Inverter placement; Collector-cable routing; Inter-block gap allowance; Multi-objective optimization